- Structural system
- Log home (Real Log Homes) and timber frame (Timberlyne) packages via dealers
- Package $/sq ft
- $85–$155
- Turnkey waterfront $/sq ft
- $310–$560
Preset with the Real Log Homes & Timberlyne example from this audit. Enter your own package quote and size to see the finished waterfront cost.
Two brands, two structural systems
Real Log Homes supplies log home packages, with milled log walls as the structure. Timberlyne, its sister brand, supplies timber frame and hybrid packages, where posts and beams carry the loads and a separate enclosure insulates the walls and roof. Both are sold through independent dealers, who quote the package and typically refer or coordinate local builders.
Every figure on this page is a Lakeview Building 2026 estimate built from our package-to-turnkey cost model, not a quote, price list or published figure from Real Log Homes and Timberlyne. Packages, scope tiers and pricing change; confirm current numbers in writing with Real Log Homes and Timberlyne or its authorized dealer before you budget.
The structural choice changes the erection bid more than the package price. A full log wall is stacked course by course and must be detailed for settling; a timber frame is raised in bents and then enclosed. For how each envelope handles shoreline humidity, see timber frame + SIPs vs. stick-built.
Included vs. not included in the structural package
| Item | Usually in package | Usually outside package |
|---|---|---|
| Logs or timbers, fasteners, sealants | Yes | Stacking or raising labor |
| Plans and structural drawings | Yes | Foundation and site engineering, local seal if required |
| Roof system | Depends on package level | Roofing finish and labor |
| Windows and exterior doors | Depends on package level | Often bought separately |
| Wall enclosure for timber frames | Confirm per Timberlyne quote | Installation labor |
| Crane, erection crew, staging | No | All of it |
| Foundation, MEP, finishes, site, septic | No | All of it |
Lakeview Building 2026 estimate. Dealer quotes and company materials lists control.
What local builders charge to erect a package
Erection is the work of turning a delivered package into a standing, weather-tight structure. It is usually bid separately from finishing, by crews who specialize in log or timber work.
| System | Rural crew | Resort-market crew | Main cost drivers |
|---|---|---|---|
| Milled log walls (Real Log style) | $28–$38 | $36–$48 | Course count, corners, settling details |
| Timber frame raising (Timberlyne style) | $18–$26 | $24–$35 | Bent count, crane hours, joinery |
| Hybrid log and timber | $22–$32 | $30–$40 | Interface details between systems |
| Crane, per day | $2,500–$4,000 | $3,500–$6,000 | Reach to the lot, pad, access road |
Excludes roofing, windows install and enclosure panels unless the crew bids them.
Some erection bids stop at walls and roof framing and exclude sealing, window bucks, settling hardware or crane time. Ask every crew to bid against the same package materials list and the same finish line, such as dried-in and sealed.
Stress-test a $299k log shell package — open the Timber Frame & Post-and-Beam Package vs. True Turnkey Cost Calculator with this page’s assumptions prefilled.
The 2026 cost stack for a 2,600 sq ft walkout
| Cost layer | Estimate | $/sq ft |
|---|---|---|
| Log structural package | $299,000 | $115 |
| Foundation, walkout walls, waterproofing | $105,000 | $40 |
| Erection crew and crane | $108,000 | $42 |
| Roofing materials and labor | $38,000 | $15 |
| Windows and exterior doors | $60,000 | $23 |
| HVAC, plumbing, electrical | $140,000 | $54 |
| Interior finishes, cabinets, stone, flooring | $210,000 | $81 |
| Sealing, staining, chinking labor | $22,000 | $8 |
| Septic, well, driveway, clearing | $115,000 | $44 |
| Engineering, permits, surveys | $28,000 | $11 |
| GC fee, 17% of $798,000 local hard cost | $136,000 | $52 |
| Turnkey total | $1,261,000 | $485 |
Multiplier 1,261,000 ÷ 299,000 = 4.22x, higher because the package is shell scope. Shoreline and dock excluded. Lakeview Building 2026 estimate.
Set scope to shell in the package vs. turnkey calculator to reproduce this, and audit the GC and erection contracts with the builder contract auditor.
Dealer deposits and milestones
- Dealer design or planning deposit
- Package order deposit to schedule production
- Balance before shipment, timed to foundation inspection
- Separate erection contract, often paid by stage: walls, roof, dry-in
- GC or owner-builder draws for finish work
Log and timber packages are popular in the Ozarks and the northern Rockies; the Lake of the Ozarks guide and the Flathead and Whitefish guide cover local permits and rock conditions.
Log or timber frame on a lake lot
Because one dealer can quote both systems, buyers often choose between them late. The trade-offs on the water:
| Factor | Log walls (Real Log style) | Timber frame (Timberlyne style) |
|---|---|---|
| Look | Log inside and out | Exposed timbers inside, any siding outside |
| Settling | Yes, detail every opening | Minimal in the enclosure |
| Exterior maintenance | Stain cycle on all log faces | Depends on siding choice |
| Large glass walls | Possible, more detailing | Natural fit |
| Erection labor per sq ft | $28–$48 | $18–$35 |
| Energy code path | Log-specific provisions | Conventional insulated enclosure |
Ranges are labor only, from the erection table above.
On a lake elevation with a large window wall, a timber frame or hybrid is often easier to detail; where the owner wants log walls throughout, budget for the stain cycle and settling work from the start.
Questions to ask before paying a design deposit
- Is the dealer deposit credited to the package and refundable on what terms?
- Which package level is quoted, and what is on the materials list?
- Are roof system, windows and doors included?
- Which local erection crews has the dealer worked with, and can I call their clients?
- Is freight included to a sloped lake lot, and who unloads?
- Who seals the drawings for my jurisdiction if required?
- How long is the package price held?
Frequently asked questions
How much does a Real Log Homes or Timberlyne package cost?
On Lakeview Building 2026 estimates, packages run about $85–$155 per sq ft depending on system and level, and finished waterfront homes about $310–$560 per sq ft. These are our estimates, not company prices; confirm with Real Log Homes, Timberlyne or a dealer.
What does it cost to erect a log home package?
On our 2026 model, labor to erect milled log walls runs about $28–$48 per sq ft of heated area, plus crane days at $2,500–$6,000. Timber frame raising runs somewhat less per sq ft.
What is the difference between Real Log Homes and Timberlyne?
Real Log Homes focuses on log home packages; Timberlyne on timber frame and hybrid packages. The structure differs, so the erection crew, enclosure, settling details and exterior maintenance differ too. Confirm current product lines with a dealer.
Can I be my own general contractor?
Some owners do, but on a waterfront lot you take on septic design, shoreline permits, crane logistics and scheduling. Lenders may also require a licensed builder for a construction-to-permanent loan.
How do I compare erection bids?
Give every crew the same materials list, drawings and finish line, such as dried-in and sealed, and ask them to list exclusions. Then compare crane days, crew size, schedule and references from waterfront jobs, not just the total.