The math behind the effective margin
E = [F × (H + S + G) + S + G + R] ÷ H- H = hard construction cost
- F = quoted fee %
- S = superintendent billed as cost = weeks × $2,200
- G = marked-up general conditions ≈ $1,450/month
- R = retained rebates ≈ 2.5% of materials (45% of H)
O = L × a × u ÷ (1 − u)
Owner pays = L + O × (1 + c)- L = lump sum
- a = allowance share of contract
- u = how far allowances sit below real selections
- c = change-order markup
The default inputs — $1.8M hard cost, 14 months, 18% fee, superintendent billed separately — produce an effective margin near 26.7%. More on structures in cost-plus vs. fixed-price vs. GMP and architect + GC vs. design-build.
What a fair waterfront contract looks like
| Structure | Where margin hides | Owner protection |
|---|---|---|
| Cost-plus % | Supervision billed as cost; fee on general conditions; retained rebates | Open books, but no ceiling |
| Fixed price | Low allowances; 25–35% change-order markup | Ceiling, but only on what is specified |
| GMP + shared savings | Contingency use | Open books, ceiling, 80/20 savings split |
A one-page list of every monthly cost the builder will bill (superintendent, trailer, software, dumpsters, toilets, insurance) is the single most useful document for comparing cost-plus bids.
- Fee base excludes general conditions
- Superintendent included in the fee
- Rebates credited to owner
- Allowances backed by 3 supplier quotes
- Change-order markup ≤ fee %
- GMP with 8–10% contingency, 80/20 split
Frequently asked questions
Is cost-plus a bad deal for a lake house?
No — open-book cost-plus is often the right structure for complex sloped waterfront builds where site conditions are uncertain. The risk is in how general conditions, supervision and rebates are defined. Fix those in the contract and cost-plus is transparent.
What is a normal change-order markup?
Many fixed-price contracts carry 25–35% on change orders. A fair cap is the same percentage as the builder’s fee (often 15–20%), with written approval before any work starts.
How does a GMP with shared savings work?
The builder works open-book for a fixed or capped fee up to a guaranteed maximum price that includes a contingency of 8–10%. If the job finishes under the GMP, the unused amount is split, typically 80% owner and 20% builder, which rewards the builder for saving money.
Can I use these clauses directly?
They are plain-language starting points. Hand them to your construction attorney to fit your state’s contract form (AIA A102/A114 or the builder’s own).