How the loan model works
Cash = max(0, 0.20 × (LotValue + Build + Contingency) − LotEquity) + 1.5% closing- LotEquity = appraised value − land loan (0 if buying now)
| Draw | Share of build | Typical trigger |
|---|---|---|
| 1 Foundation & walkout | 15% | Footings, walls, waterproofing inspected |
| 2 Framing / dry-in | 25% | Roof on, windows set |
| 3 MEP rough-in | 15% | Rough inspections passed |
| 4 Insulation & drywall | 15% | Insulation inspection |
| 5 Finishes & stone | 20% | Cabinets, flooring, tile |
| 6 Final / C.O. | 10% + contingency | Certificate of occupancy |
Interest accrues monthly on the drawn balance only, so the reserve is far smaller than a full year of interest on the total loan. Size the build itself with the turnkey calculator and check the builder’s contract on the contract auditor before the lender’s appraisal.
Lenders appraise the finished home “subject to completion”. Lake lots need comparable waterfront sales within the same reservoir; thin comps can reduce the loan amount, so ask the lender which appraiser panel they use.
Frequently asked questions
Does my lot count toward the down payment?
Usually yes. Most construction-to-permanent lenders credit the appraised value of a lot you own, minus any land loan, toward the 20% equity requirement. Lots bought recently may be valued at purchase price.
Why is the contingency held back?
Lenders hold 5–15% of the construction budget for overruns and release it only against approved change orders. If unused, it simply is not drawn, so you never pay interest on it.
What rate applies during construction?
Construction draws usually carry a variable or fixed construction rate, often 0.5–1.5 points above the permanent rate, which locks or floats down at conversion.
Is the interest reserve financed?
Many lenders build it into the loan; others bill monthly interest you pay from cash. The calculator shows it as part of the final loan balance.